BATTERY STORAGE Β· WEST

Battery storage project PIS039, Salt Lake County

Battery storage project PIS039, Salt Lake County is a 110 MW battery storage request withdrawn in the West interconnection queue, in Salt Lake County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
PIS039
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Lee Creek substation
Location
Salt Lake County, Utah
Technology
Battery: 110 MW
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
Underlying Interconnection Request Withdrawn
Queue status
Withdrawn
Entered queue
12 May 2023
Proposed online date
December 2025

Location

Marker shows the centre of Salt Lake County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Salt Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem