GAS Β· NYISO

Hempstead Expansion

Hempstead Expansion is a 39.0 MW gas request withdrawn in the NYISO interconnection queue, in Nassau County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandonedAug 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
341
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Covanta Energy
Connection point (POI)
Hempstead 138kV
Location
Nassau County, New York
Technology
Gas: 39.0 MW
Total requested
39.0 MW
Queue status
Withdrawn
Entered queue
2 September 2009
Withdrawn
August 2010

Location

Marker shows the centre of Nassau County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Nassau County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem