United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· MISO

Onshore wind project J490

Onshore wind project J490 is a 60.0 MW onshore wind request withdrawn in the MISO interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedSep 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J490
Grid region
MISO (Midcontinent)
Connection point (POI)
The McIntosh Substation located 0.5 miles due North of the intersection of Route 31 and Route 12, located just off Route 31. The referenced intersection is 0.73 miles NE of the city center of McIntos
Location
South Dakota
Technology
Wind: 60.0 MW
Total requested
60.0 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
11 November 2015
Proposed online date
October 2017
Withdrawn
September 2017

Location

No county location in the queue data.

Power plants in South Dakota Β· Transmission lines in South Dakota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem