SOLAR Β· ERCOT

Timberwolf Solar Increase

Timberwolf Solar Increase is a 80.0 MW solar request withdrawn in the ERCOT interconnection queue, in Upton County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0422
Grid region
ERCOT (Texas)
Developer
CED Crane Solar 2, LLC
Connection point (POI)
76635 King Mt 138kV
Location
Upton County, Texas
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
13 August 2019
Proposed online date
May 2021
Withdrawn
September 2019

Location

Marker shows the centre of Upton County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Upton County