🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Cold Creek Storage

Cold Creek Storage is a 172 MW battery storage request withdrawn in the ERCOT interconnection queue, in Schleicher County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2022 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0266
Grid region
ERCOT (Texas)
Developer
Cold Creek Solar LLC
Connection point (POI)
76003 Big Hill Substation 345kV
Location
Schleicher County, Texas
Technology
Battery: 172 MW
Total requested
172 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
17 April 2022
Proposed online date
December 2026
Withdrawn
February 2025

Location

Marker shows the centre of Schleicher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Schleicher County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem