United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· MISO

Onshore wind project G825, Brookings County

Onshore wind project G825, Brookings County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Brookings County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. ConsentedJun 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G825
Grid region
MISO (Midcontinent)
Connection point (POI)
Toronto - Bruce 115kV
Location
Brookings County, South Dakota
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 July 2007
Agreement signed
26 June 2012
Proposed online date
October 2013
Withdrawn
June 2012

Location

Marker shows the centre of Brookings County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Brookings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem