United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

SOLAR + STORAGE Β· WEST

Solar + storage project 21-096, Lake County

Solar + storage project 21-096, Lake County is a 400 MW solar + storage request withdrawn in the West interconnection queue, in Lake County, Oregon, connecting to Portland General Electric.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21-096
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
Grizzly-Malin 500 kV
Location
Lake County, Oregon
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
26 March 2021
Proposed online date
September 2025

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem