GAS · SPP

Gas project GEN-2016-177, Gaines County

Gas project GEN-2016-177, Gaines County is a 17.0 MW gas request built and operating in the SPP interconnection queue, in Gaines County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Jan 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2016-177
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
XTO-Cornell 115 kV station
Location
Gaines County, Texas
Technology
Gas: 17.0 MW
Total requested
17.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
23 January 2017
Proposed online date
July 2021
Came online
July 2021

Location

Marker shows the centre of Gaines County; the queue data does not give exact sites.