United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project 143, Uinta County

Onshore wind project 143, Uinta County is a 79.8 MW onshore wind request withdrawn in the West interconnection queue, in Uinta County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2007 (completed)
  2. Withdrawn / abandonedOct 2010 (project stopped here)
  3. ConsentedNov 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
143
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Muddy Creek Switching station on the Long Hollow-Naughton Line
Location
Uinta County, Wyoming
Technology
Wind: 79.8 MW
Total requested
79.8 MW
Service type
Network resource (NRIS)
Study phase
IA signed 11/17/08, Suspended 11/17/08, IA Terminated 10/27/10
Queue status
Withdrawn
Entered queue
22 June 2007
Agreement signed
17 November 2008
Proposed online date
December 2009
Withdrawn
October 2010

Location

Marker shows the centre of Uinta County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Uinta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem