Battery storage project J2178, Sullivan County is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Sullivan County, Indiana, connecting to HOOSIER ENERGY.
- PlanningQueued Aug 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2178
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- HOOSIER ENERGY
- Connection point (POI)
- Merom 345 kV
- Location
- Sullivan County, Indiana
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 6 August 2021
- Proposed online date
- October 2024
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Solar project J829, Sullivan CountySolar · 250 MW · under construction
- Sullivan Generating Station 1Gas · 575 MW · agreement signed
- Sullivan Generating Station 2Gas · 575 MW · agreement signed
- Trade Post Solar Energy CenterSolar · 200 MW · agreement signed
- Trade Post Energy StorageBattery storage · 50.0 MW · agreement signed
- Gas project J3604, Sullivan CountyGas · 650 MW · in study
- Gas project J3084, Sullivan CountyGas · 642 MW · in study
- Solar + storage project J3075, Sullivan CountySolar + storage · 560 MW · in study
- Merom StationGas · 530 MW · in study
- Gas project J4005, Sullivan CountyGas · 500 MW · in study
- Gas project J4021, Sullivan CountyGas · 470 MW · in study
- Gas project J3331, Sullivan CountyGas · 470 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem