🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

ASD Woodbury PA2 Solar I

ASD Woodbury PA2 Solar I is a 16.0 MW solar request withdrawn in the PJM interconnection queue, in Bedford County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-162
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Developer
ASD Woodbury PA2 Solar I LLC
Connection point (POI)
Curryville-RKB-Yellow Creek 23 kV
Location
Bedford County, Pennsylvania
Technology
Solar: 16.0 MW
Total requested
16.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
31 August 2021
Proposed online date
November 2023
Withdrawn
July 2025

Location

Marker shows the centre of Bedford County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Bedford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem