🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Texas Bluebonnet Solar

Texas Bluebonnet Solar is a 9.7 MW solar request built and operating in the ERCOT interconnection queue, in Mclennan County, Texas.

Queue statusOperating
  1. PlanningQueued May 2023 (completed)
  2. ConsentedAug 2023 (completed)
  3. Construction (completed)
  4. OperatingApr 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0580
Grid region
ERCOT (Texas)
Developer
Texas Bluebonnet Solar Partners, LLC
Connection point (POI)
3370 McGuffey POD 138 kV
Location
Mclennan County, Texas
Technology
Solar: 9.7 MW
Total requested
9.7 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
26 May 2023
Agreement signed
28 August 2023
Proposed online date
April 2025
Came online
April 2025

Location

Marker shows the centre of Mclennan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mclennan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem