United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTSun Valley BESS
Sun Valley BESS is a 101 MW other request built and operating in the ERCOT interconnection queue, in Hill County, Texas.
Request details
- Queue ID
- 22INR0429
- Grid region
- ERCOT (Texas)
- Developer
- Sun Valley Solar LLC
- Connection point (POI)
- tap 345kV 68090 Sam Sw - 3405 Tradinghouse
- Location
- Hill County, Texas
- Technology
- Other: 101 MW
- Total requested
- 101 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 6 October 2020
- Agreement signed
- 27 January 2023
- Proposed online date
- December 2023
- Came online
- December 2023
Location
Marker shows the centre of Hill County; the queue data does not give exact sites.
Other requests in Hill County
- Compadre SolarSolar Β· 406 MW Β· agreement signed
- Blue Skies BESSBattery storage Β· 306 MW Β· agreement signed
- Aquilla Lake 3 WindOnshore wind Β· 297 MW Β· agreement signed
- OCI Cobb Creek SolarSolar + storage Β· 203 MW Β· agreement signed
- OCI Cobb Creek ESSSolar + storage Β· 202 MW Β· agreement signed
- Padrino SolarSolar Β· 201 MW Β· agreement signed
- High Noon SolarSolar + storage Β· 182 MW Β· agreement signed
- Vial BESSBattery storage Β· 135 MW Β· agreement signed
- Three W SolarSolar Β· 111 MW Β· agreement signed
- Midpoint SolarSolar Β· 98.3 MW Β· agreement signed
- High Noon StorageSolar + storage Β· 94.0 MW Β· agreement signed
- Payne BattlecreekSolar Β· 85.0 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem