United States βΊ Grid βΊ Interconnection queues βΊ Michigan
BATTERY STORAGE Β· MISOBattery storage project J2788, Wayne County
Battery storage project J2788, Wayne County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Wayne County, Michigan, connecting to ITC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2788
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC
- Connection point (POI)
- Dayton 120kV Substation
- Location
- Wayne County, Michigan
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
- Proposed online date
- August 2025
- Withdrawn
- August 2025
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Other requests in Wayne County
- Gas project J1798, Wayne CountyGas Β· 25.0 MW Β· agreement signed
- Gas project J1262, Wayne CountyGas Β· 25.0 MW Β· agreement signed
- Battery storage project J3872, Wayne CountyBattery storage Β· 350 MW Β· in study
- Replacing 220 MW of coal generation with BESS; Trenton Channel 9Other Β· 220 MW Β· in study
- Battery storage project J2991, Wayne CountyBattery storage Β· 200 MW Β· in study
- Battery storage project J1902, Wayne CountyBattery storage Β· 200 MW Β· in study
- Battery storage project J1900, Wayne CountyBattery storage Β· 200 MW Β· in study
- Other project J3763, Wayne CountyOther Β· 7.5 MW Β· in study
- Gas project G023, Wayne CountyGas Β· 710 MW Β· built
- Gas project G038, Wayne CountyGas Β· 360 MW Β· built
- Gas project G026, Wayne CountyGas Β· 240 MW Β· built
- Gas project J440, Wayne CountyGas Β· 52.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem