πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

BATTERY STORAGE Β· MISO

Battery storage project J2788, Wayne County

Battery storage project J2788, Wayne County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Wayne County, Michigan, connecting to ITC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2788
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
Dayton 120kV Substation
Location
Wayne County, Michigan
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
August 2025
Withdrawn
August 2025

Location

Marker shows the centre of Wayne County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Wayne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem