πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Carolina

OTHER Β· SOUTHEAST

Other project PP00030, Dillon County

Other project PP00030, Dillon County is a 65.0 MW other request withdrawn in the Southeast interconnection queue, in Dillon County, South Carolina, connecting to Duke Energy Progress.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
PP00030
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
Weatherspoon - Latta 230
Location
Dillon County, South Carolina
Technology
Other: 65.0 MW
Total requested
65.0 MW
Study phase
Provisional IR Withdrawn
Queue status
Withdrawn
Entered queue
3 June 2025
Proposed online date
December 2027

Location

Marker shows the centre of Dillon County; the queue data does not give exact sites.

Power plants in South Carolina Β· Transmission lines in South Carolina

Other requests in Dillon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem