Midway Wind

Midway Wind is a 163 MW onshore wind request built and operating in the ERCOT interconnection queue, in San Patricio County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2009 (completed)
  2. ConsentedNov 2017 (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
11INR0054
Grid region
ERCOT (Texas)
Developer
Apex Clean
Connection point (POI)
8961 Whitepoint 138kV
Location
San Patricio County, Texas
Technology
Wind: 163 MW
Total requested
163 MW
Study phase
IA
Queue status
Operational
Entered queue
25 February 2009
Agreement signed
5 November 2017
Proposed online date
June 2019
Came online
December 2018

Location

Marker shows the centre of San Patricio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in San Patricio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem