Solar project AH1-076, Westmoreland County

Solar project AH1-076, Westmoreland County is a 18.0 MW solar request withdrawn in the PJM interconnection queue, in Westmoreland County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-076
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
CP Loyalhanna Creek LLC
Connection point (POI)
Loyalhanna - Reed Junction 25 kV
Location
Westmoreland County, Pennsylvania
Technology
Solar: 18.0 MW
Total requested
18.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
29 July 2021
Proposed online date
December 2023
Withdrawn
March 2025

Location

Marker shows the centre of Westmoreland County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Westmoreland County