πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

BATTERY STORAGE Β· NYISO

Blue Frost

Blue Frost is a 400 MW battery storage request withdrawn in the NYISO interconnection queue, in Montgomery County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1604
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Blue Frost Energy Center, LLC
Connection point (POI)
Marcy - New Scotland 345 kV
Location
Montgomery County, New York
Technology
Battery: 400 MW
Total requested
400 MW
Queue status
Withdrawn
Entered queue
5 September 2023

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem