πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4350 MW
Active in queue350 MW4 requests
Agreement signed4.6 MW1 requests
Withdrawn11712.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project IA-PNM-2012-05, Guadalupe Cty County
Onshore wind
198 MWIn study Guadalupe Cty, NMWest Dec 2012target 2015
Onshore wind project 12-053, Polk County
Onshore wind
87.5 MWPaused / redesign Polk, ORWest Oct 2012target 2015
Onshore wind project GI-2012-3, Logan County
Onshore wind
60.0 MWIn study Logan, COWest May 2012target 2013
Berkshire Wind Increase
Onshore wind
4.6 MWAgreement signed Berkshire, MAISO-NE Aug 2012target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)