Onshore wind interconnection queue in the USA (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,541 MW
Active in queue1,541 MW7 requests
Agreement signed741 MW4 requests
Withdrawn19436.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 11-043, Umatilla County
Onshore wind
400 MWPaused / redesign Umatilla, ORWest Jun 2011target 2014
Onshore wind project 11-040, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Onshore wind project GI-2011-7, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Aug 2011target 2012
Onshore wind project 11-039, Gilliam County
Onshore wind
200 MWPaused / redesign Gilliam, ORWest Mar 2011target 2015
Onshore wind project GI-2011-2, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Mar 2011target 2012
Onshore wind project GEN-2011-019, Woodward County
Onshore wind
175 MWAgreement signed Woodward, OKSPP Mar 2011target 2027
Onshore wind project GEN-2011-020, Ellis County
Onshore wind
166 MWAgreement signed Ellis, OKSPP Mar 2011target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)