United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Hydro interconnection queue in the USA (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown518.6 MW
Active in queue18.6 MW5 requests
Agreement signed3.3 MW2 requests
Withdrawn21,303 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project 590, Marion County
Hydro
7.0 MWIn study Marion, TNSoutheast Nov 2023target 2028
Hydro project 899433, Montgomery County
Hydro Β· Duke Energy Progress, LLC
6.3 MWUnder construction Montgomery, NCSoutheast Jun 2023
Hydro project 897387, Macon County
Hydro
2.0 MWUnder construction Macon, NCSoutheast Jun 2023
Hydro project 899609, Jackson County
Hydro
1.8 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026
Hydro project 899793, Jackson County
Hydro
1.5 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)