Geothermal interconnection queue in the USA (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4386 MW
Active in queue386 MW4 requests
Agreement signed38.5 MW1 requests
Withdrawn3555 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project GI-2023-174, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Geothermal project GI-2023-176, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Geothermal project Company QK, Lyon County
Geothermal
38.5 MWAgreement signed Lyon, NVWest Sep 2023target 2030
Geothermal project GI-2023-177, Imperial County
Geothermal
33.0 MWIn study Imperial, CAWest Apr 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)