United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in the USA (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4102 MW
Active in queue102 MW4 requests
Agreement signed102 MW4 requests
Withdrawn8234.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bergen Generating Station
Gas
51.1 MWAgreement signed Bergen, NJPJM Apr 20162019
Glen Falls Facility
Gas
30.0 MWAgreement signed Harrison, WVPJM Sep 2016target 2029
Gas project 304, Shelby County
Gas
14.0 MWAgreement signed Shelby, TNSoutheast Nov 2016target 2018
Gas project J571, Kalamazoo County
Gas
6.4 MWAgreement signed Kalamazoo, MIMISO May 2016target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)