United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in the USA (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown84,275 MW
Active in queue4,275 MW8 requests
Agreement signed1,948 MW4 requests
Withdrawn12744.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 257, Shelby County
Gas
1,132 MWAgreement signed Shelby, TNSoutheast Aug 2014target 2018
Gas project G0501, Klamath County
Gas
1,100 MWIn study Klamath, ORWest Oct 2014target 2018
FGE Texas 2 Gas
Gas Β· FGE Power
743 MWPaused / redesign Mitchell, TXERCOT Feb 2014target 2028
Gas project J351, St. Joseph County
Gas
715 MWAgreement signed St. Joseph, INMISO May 2014target 2020
Halyard Wharton
Gas Β· Halyard Energy
484 MWPaused / redesign Wharton, TXERCOT Mar 2014target 2021
Gas project IA-PNM-2014-02, San Juan County
Gas
80.0 MWAgreement signed San Juan, NMWest Feb 2014target 2018
Gas project J384, Dane County
Gas
21.0 MWAgreement signed Dane, WIMISO Aug 2014target 2017
Gas project 41, Lincoln County
Gas
0.3 MWIn study Lincoln, WAWest Apr 2014target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)