United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,371 MW
Active in queue3,270 MW17 requests
Agreement signed1,371 MW10 requests
Withdrawn46255.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project LGE-GIS-2013-001, Jefferson County
Gas
691 MWAgreement signed Jefferson, KYSoutheast Aug 2013target 2015
Onshore wind project GI-2013-5, Arapahoe County
Onshore wind
201 MWAgreement signed Arapahoe, COWest Jul 20132014
Harald (BearKat Wind B)
Onshore wind Β· McCrae Wind Energy II, LLC
162 MWAgreement signed Glasscock, TXERCOT Nov 2013target 2026
Sunshine Valley Solar 1
Solar + storage
90.0 MWAgreement signed Nye, NVCAISO Apr 2013target 2026
Solar project GEN-2013-019, Lancaster County
Solar
73.6 MWAgreement signed Lancaster, NESPP Apr 2013target 2026
Solar project GEN-2013-002, Lancaster County
Solar
50.6 MWAgreement signed Lancaster, NESPP Mar 2013target 2026
Gas project IA-PNM-2013-01, Valencia County
Gas
42.3 MWAgreement signed Valencia, NMWest May 2013target 2017
Rio Bravo Solar 2
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Apr 20132016
Onshore wind project GI-2013-4, Jefferson County
Onshore wind
19.9 MWAgreement signed Jefferson, COWest Jun 2013target 2015
Lassen Lodge Hydroelectric 2
Hydro
0.5 MWAgreement signed Tehama, CACAISO Apr 2013target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)