Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown92,150 MW
Active in queue2,150 MW9 requests
Agreement signed600 MW2 requests
Withdrawn71,494 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 607, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project CLPT G17, Laramie County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Other project CLPT G16, Platte County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Platte, WYWest Apr 2022target 2025
Other project 608, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project 37681, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Other project 38047, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Other project 38412, Goshen County
Other
200 MWIn study Goshen, WYWest Jul 2025target 2029
Other project 609, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
200 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project CLPT G29, Laramie County
Other
150 MWIn study Laramie, WYWest May 2024target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)