United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Wyoming (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown112,681 MW
Active in queue1,933 MW13 requests
Agreement signed250 MW1 requests
Withdrawn112,681 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C4-085, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Solar + storage project C4-042, Carbon County
Solar + storage
330 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Onshore wind project C4-036, Carbon County
Onshore wind
310 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2031
Wind + storage project CLPT G28, Converse County
Wind + storage
300 MWWithdrawn / abandoned Converse, WYWest Jan 2024target 2026
Battery storage project C4-050, Sweetwater County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest May 2024target 2028
Battery storage project PIS083, Sweetwater County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2024target 2028
Battery storage project C4-049, Carbon County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2028
Battery storage project PIS084, Carbon County
Battery storage Β· PacifiCorp
200 MWWithdrawn / abandoned Carbon, WYWest Jun 2024target 2028
Solar + storage project C4-025, Natrona County
Solar + storage
199 MWWithdrawn / abandoned Natrona, WYWest May 2024target 2028
Onshore wind project C4-035, Carbon County
Onshore wind
182 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2031
Solar + storage project C4-109, Albany County
Solar + storage
160 MWWithdrawn / abandoned Albany, WYWest May 2024target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)