United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Wyoming (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown112,818 MW
Active in queue2,338 MW7 requests
Agreement signed790 MW2 requests
Withdrawn112,818 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project C1-25, Carbon County
Battery storage
900 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2028
Onshore wind project C1-48, Sweetwater County
Onshore wind
600 MWWithdrawn / abandoned Sweetwater, WYWest May 2021target 2025
Solar + storage project C1-59, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest May 2021target 2024
Solar + storage project C1-38, Uinta County
Solar + storage
200 MWWithdrawn / abandoned Uinta, WYWest May 2021target 2024
Solar + storage project C1-55, Carbon County
Solar + storage
199 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2025
Onshore wind project C1-53, Albany County
Onshore wind
190 MWWithdrawn / abandoned Albany, WYWest May 2021target 2024
Solar project CLPT G15, Laramie County
Solar Β· Cheyenne Light, Fuel & Power
150 MWWithdrawn / abandoned Laramie, WYWest Jul 2021target 2025
Solar + storage project 21-08241, Laramie County
Solar + storage
150 MWWithdrawn / abandoned Laramie, WYWest Aug 2021target 2025
Onshore wind project C1-57, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2025
Solar project C1-02, Park County
Solar
20.0 MWWithdrawn / abandoned Park, WYWest Apr 2021target 2025
Solar project C1-03, Park County
Solar
9.0 MWWithdrawn / abandoned Park, WYWest Apr 2021target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)