Projects with signed interconnection agreements in Washington (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5430 MW
Active in queue3,657 MW22 requests
Agreement signed430 MW5 requests
Withdrawn494,360 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 60, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Aug 2018target 2028
Solar + storage project 1008, Yakima County
Solar + storage Β· Black Rock Solar, LLC
94.0 MWAgreement signed Yakima, WAWest Mar 2018target 2023
Other project 66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest Jul 2018target 2026
Solar + storage project 59, Adams County
Solar + storage
60.0 MWAgreement signed Adams, WAWest May 2018
Solar project TCS-14, Yakima County
Solar Β· OneEnergy Development, LLC
5.0 MWAgreement signed Yakima, WAWest Oct 2018target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)