Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown192,151 MW
Active in queue2,151 MW19 requests
Agreement signed551 MW6 requests
Withdrawn21613.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project PIS024, Utah County
Solar
200 MWIn study Utah, UTWest Jul 2022target 2025
Solar project PIS043, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar project PIS042, Utah County
Solar
199 MWIn study Utah, UTWest Jun 2023target 2026
Solar project PIS056, Emery County
Solar Β· PacifiCorp
178 MWIn study Emery, UTWest May 2024target 2026
Solar project 823, Emery County
Solar Β· PacifiCorp Energy Supply Management
178 MWAgreement signed Emery, UTWest Nov 2016target 2027
Solar project PIS027, Utah County
Solar
150 MWIn study Utah, UTWest Jul 2022target 2025
Solar project PIS057, Emery County
Solar Β· PacifiCorp
125 MWIn study Emery, UTWest May 2024target 2026
Solar project C2-167, Emery County
Solar Β· PacifiCorp
125 MWIn study Emery, UTWest May 2022target 2026
Solar project 634, Beaver County
Solar Β· Fremont Solar, LLC
99.0 MWAgreement signed Beaver, UTWest Nov 2014target 2025
Solar project C2-169, Tooele County
Solar Β· PacifiCorp
99.0 MWPaused / redesign Tooele, UTWest May 2022target 2026
Solar project 636, Iron County
Solar Β· Rush Lake Solar, LLC
99.0 MWAgreement signed Iron, UTWest Dec 2014target 2025
Solar project 805, Kane County
Solar Β· Glen Canyon Solar A, LLC
95.0 MWIn study Kane, UTWest Sep 2016target 2019
Solar project 781, Tooele County
Solar Β· Elektron Solar, LLC
80.0 MWAgreement signed Tooele, UTWest Aug 2016target 2023
Solar project S0020, Tooele County
Solar
80.0 MWIn study Tooele, UTWest Dec 2022target 2026
Solar project 846, Tooele County
Solar Β· Horseshoe Solar, LLC
75.0 MWAgreement signed Tooele, UTWest Jan 2017target 2023
Solar project C2-168, Emery County
Solar Β· PacifiCorp
70.0 MWIn study Emery, UTWest May 2022target 2026
Solar project PIS058, Emery County
Solar Β· PacifiCorp
70.0 MWIn study Emery, UTWest May 2024target 2026
Solar project 815, Emery County
Solar Β· Pivot 13, LLC
20.0 MWAgreement signed Emery, UTWest Nov 2016target 2025
Solar project T2-058, Box Elder County
Solar
10.0 MWIn study Box Elder, UTWest Sep 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)