πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Utah

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown182,814 MW
Active in queue2,814 MW18 requests
Agreement signed0.0 MW0 requests
Withdrawn4712.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project T2-020, Juab County
Gas Β· PacifiCorp
363 MWIn study Juab, UTWest Sep 2025target 2029
Gas project S0035, Washington County
Gas
300 MWIn study Washington, UTWest Apr 2025target 2027
Gas project PIS040, Utah County
Gas
300 MWIn study Utah, UTWest Jun 2023target 2026
Gas project T2-059, Utah County
Gas
300 MWIn study Utah, UTWest Sep 2025target 2025
Gas project S0021, Utah County
Gas
200 MWIn study Utah, UTWest Oct 2023target 2025
Gas project C2-05, Juab County
Gas Β· PacifiCorp
200 MWIn study Juab, UTWest Apr 2022target 2026
Gas project PIS009, Juab County
Gas Β· PacifiCorp
200 MWIn study Juab, UTWest Jun 2022target 2026
Gas project PIS012, Juab County
Gas Β· PacifiCorp
200 MWIn study Juab, UTWest Jun 2022target 2026
Gas project C2-02, Juab County
Gas Β· PacifiCorp
200 MWIn study Juab, UTWest Apr 2022target 2026
Gas project T2-035, Millard County
Gas
185 MWIn study Millard, UTWest Sep 2025target 2029
Gas project PIS092, Utah County
Gas Β· PacifiCorp
73.0 MWIn study Utah, UTWest Oct 2024target 2026
Gas project PIS093, Juab County
Gas Β· PacifiCorp
71.0 MWIn study Juab, UTWest Oct 2024target 2026
Gas project PIS090, Utah County
Gas Β· PacifiCorp
62.0 MWIn study Utah, UTWest Oct 2024target 2026
Gas project T2-014, Juab County
Gas Β· PacifiCorp
56.0 MWIn study Juab, UTWest Aug 2025target 2028
Gas project T2-019, Utah County
Gas Β· PacifiCorp
55.0 MWIn study Utah, UTWest Aug 2025target 2028
Gas project T2-018, Utah County
Gas Β· PacifiCorp
25.0 MWIn study Utah, UTWest Aug 2025target 2026
Gas project PIS091, Salt Lake County
Gas Β· PacifiCorp
17.0 MWIn study Salt Lake, UTWest Oct 2024target 2026
Gas project T2-015, Salt Lake County
Gas Β· PacifiCorp
7.0 MWIn study Salt Lake, UTWest Aug 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)