United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Utah (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31,020 MW
Active in queue8,577 MW48 requests
Agreement signed0.0 MW0 requests
Withdrawn31,020 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project T2-092, Millard County
Onshore wind
600 MWWithdrawn / abandoned Millard, UTWest Sep 2025target 2028
Solar + storage project T2-091, Iron County
Solar + storage
400 MWWithdrawn / abandoned Iron, UTWest Sep 2025target 2027
Geothermal project T2-001, Iron County
Geothermal
20.0 MWWithdrawn / abandoned Iron, UTWest Jul 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)