United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Utah (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12355 MW
Active in queue198 MW2 requests
Agreement signed198 MW2 requests
Withdrawn331,232 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 631, Beaver County
Solar Β· Milford Solar I, LLC
99.0 MWOperating Beaver, UTWest Nov 2014target 2020
Solar project 551, Beaver County
Solar Β· Escalante Solar III, LLC
80.0 MWOperating Beaver, UTWest Feb 2014target 2016
Solar project 564, Iron County
Solar Β· Three Peaks Power, LLC
80.0 MWOperating Iron, UTWest Apr 2014target 2016
Solar project 589, Sevier County
Solar Β· Sigurd Solar, LLC
80.0 MWOperating Sevier, UTWest Jul 2014target 2020
Other project 548, Washington County
Other Β· Utah Associated Municipal Power Systems
6.0 MWOperating Washington, UTWest Feb 2014target 2016
Other project 549, Salt Lake County
Other Β· eBay, Inc.
3.6 MWOperating Salt Lake, UTWest Feb 2014target 2014
Solar project 632, Beaver County
Solar Β· Thermo No. 1 BE-01, LLC
3.0 MWOperating Beaver, UTWest Nov 2014target 2017
Onshore wind project 638, Tooele County
Onshore wind Β· Tooele Army Depot
1.7 MWOperating Tooele, UTWest Dec 2014target 2016
Solar project 630, Davis County
Solar Β· Smith's Food & Drug Stores, Inc.
1.0 MWOperating Davis, UTWest Oct 2014target 2015
Solar project 560, Salt Lake County
Solar Β· Salt Lake Community College
0.4 MWOperating Salt Lake, UTWest Apr 2014target 2015
Solar project 562, Salt Lake County
Solar Β· U of U Solar 2, LLC
0.1 MWOperating Salt Lake, UTWest Apr 2014target 2015
Solar project 563, Salt Lake County
Solar Β· U of U Solar 2, LLC
0.0 MWOperating Salt Lake, UTWest Apr 2014target 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)