OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Tennessee (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3357 MW
Active in queue357 MW3 requests
Agreement signed357 MW3 requests
Withdrawn91,021 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 501, Bledsoe County
Solar
150 MWAgreement signed Bledsoe, TNSoutheast May 2022target 2025
Solar project 510, Carroll County
Solar
140 MWAgreement signed Carroll, TNSoutheast Jul 2022target 2029
Solar project 515, Haywood County
Solar
67.0 MWAgreement signed Haywood, TNSoutheast Aug 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)