United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Tennessee (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2788 MW
Active in queue788 MW2 requests
Agreement signed788 MW2 requests
Withdrawn162,764 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 401, Humphreys County
Gas
593 MWAgreement signed Humphreys, TNSoutheast Sep 2019target 2023
Solar project 374, Lawrence County
Solar
195 MWAgreement signed Lawrence, TNSoutheast Jun 2019target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)