United States β€Ί Grid β€Ί Interconnection queues β€Ί Tennessee

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Tennessee (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown162,220 MW
Active in queue303 MW3 requests
Agreement signed303 MW3 requests
Withdrawn162,220 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 484, Shelby County
Battery storage
300 MWWithdrawn / abandoned Shelby, TNSoutheast Sep 2020
Solar project 459, Cocke County
Solar
200 MWWithdrawn / abandoned Cocke, TNSoutheast Sep 2020
Solar project 442, Cumberland County
Solar
200 MWWithdrawn / abandoned Cumberland, TNSoutheast Jun 2020
Solar project 439, Mcminn County
Solar
200 MWWithdrawn / abandoned Mcminn, TNSoutheast Jun 2020
Solar project 438, Robertson County
Solar
200 MWWithdrawn / abandoned Robertson, TNSoutheast Jun 2020
Solar + storage project 434, Haywood County
Solar + storage
175 MWWithdrawn / abandoned Haywood, TNSoutheast May 2020target 2023
Solar project 460, Grundy County
Solar
150 MWWithdrawn / abandoned Grundy, TNSoutheast Sep 2020target 2023
Solar project 413, Putnam County
Solar
120 MWWithdrawn / abandoned Putnam, TNSoutheast Jan 2020
Solar + storage project 458, Tipton County
Solar + storage
120 MWWithdrawn / abandoned Tipton, TNSoutheast Sep 2020
Solar + storage project 444, Mcnairy County
Solar + storage
100 MWWithdrawn / abandoned Mcnairy, TNSoutheast Jun 2020
Solar project 465, Bedford County
Solar
100 MWWithdrawn / abandoned Bedford, TNSoutheast Dec 2020
Solar + storage project 457, Polk County
Solar + storage
100 MWWithdrawn / abandoned Polk, TNSoutheast Sep 2020
Solar project 436, Greene County
Solar
90.0 MWWithdrawn / abandoned Greene, TNSoutheast Jun 2020
Solar project 462, Lawrence County
Solar
80.0 MWWithdrawn / abandoned Lawrence, TNSoutheast Dec 2020
Solar project 430, Lake County
Solar
68.0 MWWithdrawn / abandoned Lake, TNSoutheast May 2020
Battery storage project 435, Lake County
Battery storage
17.0 MWWithdrawn / abandoned Lake, TNSoutheast Jun 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)