πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in South Dakota (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2299 MW
Active in queue299 MW2 requests
Agreement signed0.0 MW0 requests
Withdrawn6732 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-1501, Bon Homme County
Onshore wind
200 MWIn study Bon Homme, SDWest Feb 2015
Onshore wind project GI-1505, Brown County
Onshore wind
99.0 MWIn study Brown, SDWest Apr 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)