πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in South Dakota (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,500 MW
Active in queue1,080 MW6 requests
Agreement signed880 MW5 requests
Withdrawn122,500 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2022-020, Walworth County
Solar
355 MWWithdrawn / abandoned Walworth, SDSPP Jun 20222025
Onshore wind project GEN-2022-034, Union County
Onshore wind
300 MWWithdrawn / abandoned Union, SDSPP Jun 20222025
Onshore wind project GEN-2022-068, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project GEN-2022-069, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project GEN-2022-070, Hyde County
Onshore wind
250 MWWithdrawn / abandoned Hyde, SDSPP Aug 2022target 2026
Onshore wind project J2338, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDMISO Sep 2022target 2027
Onshore wind project J2333, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDMISO Sep 2022target 2027
Onshore wind project J2546, Deuel County
Onshore wind
185 MWWithdrawn / abandoned Deuel, SDMISO Sep 2022target 2027
Solar project J3017, Grant County
Solar
150 MWWithdrawn / abandoned Grant, SDMISO Sep 2022target 2027
Solar project GEN-2022-066, Perkins County
Solar
150 MWWithdrawn / abandoned Perkins, SDSPP Aug 2022target 2028
Solar + storage project J3183, Grant County
Solar + storage
125 MWWithdrawn / abandoned Grant, SDMISO Sep 2022target 2027
Solar project GEN-2022-067, Meade County
Solar
85.0 MWWithdrawn / abandoned Meade, SDSPP Aug 2022target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)