United States β€Ί Grid β€Ί Interconnection queues β€Ί South Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in South Carolina (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown362,127 MW
Active in queue69.8 MW1 requests
Agreement signed69.8 MW1 requests
Withdrawn362,127 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

36 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 15918, Sumter County
Solar Β· Duke Energy Renewables Solar LLC
100 MWWithdrawn / abandoned Sumter, SCSoutheast Jun 2017
Solar project 65, Richland County
Solar
100 MWWithdrawn / abandoned Richland, SCSoutheast Dec 2017target 2019
Solar project 66, Fairfield County
Solar
100 MWWithdrawn / abandoned Fairfield, SCSoutheast Dec 2017target 2019
Solar project 49, Lexington County
Solar
100 MWWithdrawn / abandoned Lexington, SCSoutheast Nov 2017target 2019
Solar project 64, Richland County
Solar
100 MWWithdrawn / abandoned Richland, SCSoutheast Dec 2017target 2019
Solar project 68, Marion County
Solar
100 MWWithdrawn / abandoned Marion, SCSoutheast Dec 2017target 2019
Solar project 67, Newberry County
Solar
100 MWWithdrawn / abandoned Newberry, SCSoutheast Dec 2017target 2019
Solar project 51, Beaufort County
Solar
100 MWWithdrawn / abandoned Beaufort, SCSoutheast Nov 2017target 2019
Solar project 50, Georgetown County
Solar
100 MWWithdrawn / abandoned Georgetown, SCSoutheast Nov 2017target 2019
Solar project 17658, Marion County
Solar
80.0 MWWithdrawn / abandoned Marion, SCSoutheast Oct 2017
Solar project 56, Berkeley County
Solar
75.0 MWWithdrawn / abandoned Berkeley, SCSoutheast Nov 2017target 2019
Solar project 70688, Greenwood County
Solar
75.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Sep 2017
Solar project 61, Dillon County
Solar
75.0 MWWithdrawn / abandoned Dillon, SCSoutheast Nov 2017target 2019
Solar project 57, Williamsburg County
Solar
75.0 MWWithdrawn / abandoned Williamsburg, SCSoutheast Nov 2017target 2019
Solar project 58, Barnwell County
Solar
75.0 MWWithdrawn / abandoned Barnwell, SCSoutheast Nov 2017target 2019
Solar project 59, Aiken County
Solar
75.0 MWWithdrawn / abandoned Aiken, SCSoutheast Nov 2017target 2019
Solar project 60, Clarendon County
Solar
75.0 MWWithdrawn / abandoned Clarendon, SCSoutheast Nov 2017target 2019
Solar project 43, Orangeburg County
Solar
75.0 MWWithdrawn / abandoned Orangeburg, SCSoutheast Apr 2017target 2019
Solar project 55, Allendale County
Solar
75.0 MWWithdrawn / abandoned Allendale, SCSoutheast Nov 2017target 2019
Solar project 52, Colleton County
Solar
75.0 MWWithdrawn / abandoned Colleton, SCSoutheast Nov 2017target 2019
Solar project 17236, Lee County
Solar Β· Masked
75.0 MWWithdrawn / abandoned Lee, SCSoutheast Aug 2017
Solar project 53, Newberry County
Solar
75.0 MWWithdrawn / abandoned Newberry, SCSoutheast Nov 2017target 2019
Solar project 16321, Chesterfield County
Solar
70.0 MWWithdrawn / abandoned Chesterfield, SCSoutheast Jun 2017
Solar project 5649, Chesterfield County
Solar Β· Duke Energy Progress, LLC
50.0 MWWithdrawn / abandoned Chesterfield, SCSoutheast Jun 2017
Solar project 16298, Chester County
Solar
39.0 MWWithdrawn / abandoned Chester, SCSoutheast Aug 2017
Solar project 62756, Greenwood County
Solar
32.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Nov 2017
Solar project 30584, Darlington County
Solar
20.0 MWWithdrawn / abandoned Darlington, SCSoutheast May 2017
Solar project 30360, Chesterfield County
Solar
20.0 MWWithdrawn / abandoned Chesterfield, SCSoutheast May 2017
Solar project 16326, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Nov 2017
Solar project 16328, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2017
Solar project 16257, Darlington County
Solar
2.0 MWWithdrawn / abandoned Darlington, SCSoutheast Sep 2017
Solar project 16327, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Nov 2017
Solar project 19156, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2017target 2022
Solar project 19176, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Nov 2017
Solar project 19170, Marlboro County
Solar
2.0 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2017
Solar project 19139, Dillon County
Solar
2.0 MWWithdrawn / abandoned Dillon, SCSoutheast Oct 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)