SOLAR Β· SOUTHEAST

Solar project 19156, Marlboro County

Solar project 19156, Marlboro County is a 2.0 MW solar request withdrawn in the Southeast interconnection queue, in Marlboro County, South Carolina, connecting to Duke Energy Progress.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
19156
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
BENNETTSVILLE 230KV
Location
Marlboro County, South Carolina
Technology
Solar: 2.0 MW
Total requested
2.0 MW
Service type
Other
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
10 October 2017
Proposed online date
March 2022

Location

Marker shows the centre of Marlboro County; the queue data does not give exact sites.

Power plants in South Carolina Β· Transmission lines in South Carolina

Other requests in Marlboro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem