Requests shown351,209 MW
Active in queue1,209 MW35 requests
Agreement signed0.0 MW0 requests
Withdrawn61,822 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

35 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AI2-443, Greene County
Solar + storage
300 MWIn study Greene, PAPJM Mar 2023target 2027
Solar + storage project AI2-446, Cambria County
Solar + storage
150 MWIn study Cambria, PAPJM Mar 2023target 2027
Battery storage project AJ1-016, Cambria County
Battery storage
100 MWIn study Cambria, PAPJM Jun 2023target 2028
Solar project AI2-063, Mckean County
Solar
82.5 MWIn study Mckean, PAPJM Feb 2023target 2027
Solar project AI2-195, Lycoming County
Solar
69.9 MWIn study Lycoming, PAPJM Mar 2023target 2025
Solar project AI2-196, Lycoming County
Solar
51.5 MWIn study Lycoming, PAPJM Mar 2023target 2025
Solar project AI2-475, Montour County
Solar
40.6 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-474, Montour County
Solar
34.8 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-471, Montour County
Solar
29.5 MWIn study Montour, PAPJM Mar 2023target 2025
Solar project AI2-473, Montour County
Solar
29.0 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-154, Centre County
Solar
24.0 MWIn study Centre, PAPJM Mar 2023target 2025
Solar project AI2-415, Butler County
Solar
20.3 MWIn study Butler, PAPJM Mar 2023target 2026
Solar + storage project AI2-435, Berks County
Solar + storage
20.0 MWIn study Berks, PAPJM Mar 2023target 2026
Solar + storage project AI2-442, Luzerne County
Solar + storage
20.0 MWIn study Luzerne, PAPJM Mar 2023target 2027
Solar + storage project AI2-439, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Mar 2023target 2027
Solar + storage project AI2-436, Clearfield County
Solar + storage
20.0 MWIn study Clearfield, PAPJM Mar 2023target 2026
Solar + storage project AI2-441, Luzerne County
Solar + storage
20.0 MWIn study Luzerne, PAPJM Mar 2023target 2027
Solar + storage project AI2-440, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Mar 2023target 2027
Solar + storage project AI2-434, Lycoming County
Solar + storage
20.0 MWIn study Lycoming, PAPJM Mar 2023target 2026
Solar project AI2-061, Somerset County
Solar
17.6 MWIn study Somerset, PAPJM Feb 2023target 2026
Solar project AI2-472, Montour County
Solar
14.5 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI2-485, Butler County
Solar
14.0 MWIn study Butler, PAPJM Mar 2023target 2028
Solar project AI2-486, Fayette County
Solar
14.0 MWIn study Fayette, PAPJM Mar 2023target 2028
Solar project AI2-414, Berks County
Solar
12.5 MWIn study Berks, PAPJM Mar 2023target 2026
Solar project AI2-310, Venango County
Solar
7.3 MWIn study Venango, PAPJM Mar 2023target 2025
Solar project AI2-057, Venango County
Solar
6.6 MWIn study Venango, PAPJM Feb 2023target 2024
Solar project AI2-458, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-476, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AI2-467, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-469, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-459, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-470, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-477, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AI2-312, Venango County
Solar
5.5 MWIn study Venango, PAPJM Mar 2023target 2022
Solar project AI2-308, Bedford County
Solar
4.4 MWIn study Bedford, PAPJM Mar 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)