United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Pennsylvania (2014 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Hatfield Ferry, Units 1, 2, and 3 Coal |
1,710 MW | Withdrawn / abandoned |
| Gas project Z2-026, Berks County Gas |
800 MW | Withdrawn / abandoned |
| Gas project Z2-064, Washington County Gas |
651 MW | Withdrawn / abandoned |
| Renovo Energy Center Gas |
463 MW | Withdrawn / abandoned |
| Gas project AA1-045, Venango County Gas |
308 MW | Withdrawn / abandoned |
| Other project AA1-017, Monroe County Other |
243 MW | Withdrawn / abandoned |
| Onshore wind project AA1-103, Carbon County Onshore wind |
209 MW | Withdrawn / abandoned |
| Gas project AA1-036, Luzerne County Gas |
180 MW | Withdrawn / abandoned |
| Gateway Bradford Plant Gas |
163 MW | Withdrawn / abandoned |
| Other project AA1-016, Monroe County Other |
158 MW | Withdrawn / abandoned |
| Penn Forest Wind Project Onshore wind |
98.0 MW | Withdrawn / abandoned |
| Centre County Wind Facility Onshore wind |
82.0 MW | Withdrawn / abandoned |
| Kimberly Run Wind Farm Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project AA1-113, Schuylkill County Onshore wind |
68.0 MW | Withdrawn / abandoned |
| Onshore wind project Z2-101, Schuylkill County Onshore wind |
67.5 MW | Withdrawn / abandoned |
| Onshore wind project AA1-114, Carbon County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Battery storage project AA1-115, Blair County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Gas project AA1-106, Tioga County Gas |
19.9 MW | Withdrawn / abandoned |
| Ten Mile Generation Facility Gas |
19.9 MW | Withdrawn / abandoned |
| Amity Generation Facility Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA1-041, Tioga County Gas |
19.9 MW | Withdrawn / abandoned |
| Solar project Z2-015, Allegheny County Solar |
19.8 MW | Withdrawn / abandoned |
| Northumberland Wood Fired Power Plant Other |
16.0 MW | Withdrawn / abandoned |
| Waymart Battery Energy Storage System Battery storage |
10.0 MW | Withdrawn / abandoned |
| Bradford Natural Gas Facility Gas |
8.0 MW | Withdrawn / abandoned |
| Westmoreland Landfill Project Other |
7.2 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)