United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in Oregon

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3316.2 GW
Active in queue16.2 GW33 requests
Agreement signed0.0 MW0 requests
Withdrawn575,577 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

33 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G0695, Crook County
Other
3,600 MWIn study Crook, ORWest Sep 2021target 2028
Other project G0675, Crook County
Other
1,800 MWIn study Crook, ORWest Mar 2021target 2029
Other project G0864, Sherman County
Other
1,304 MWIn study Sherman, ORWest May 2023target 2027
Other project G0787, Wasco County
Other
1,200 MWIn study Wasco, ORWest Aug 2022target 2028
Other project 23-229, Jefferson County
Other
750 MWIn study Jefferson, ORWest Mar 2023target 2027
Other project G0806, Douglas County
Other
600 MWIn study Douglas, ORWest Sep 2022target 2028
Other project G0854, Umatilla County
Other
600 MWIn study Umatilla, ORWest Apr 2023target 2025
Other project G0811, Lane County
Other
600 MWIn study Lane, ORWest Sep 2022target 2030
Other project G0768, Gilliam County
Other
600 MWIn study Gilliam, ORWest Aug 2022target 2027
Other project G0895, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0893, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0904, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0899, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0902, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0905, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0894, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0892, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project 771, Baker County
Other
325 MWIn study Baker, ORWest Apr 2025target 2029
Other project G0693, Crook County
Other
300 MWIn study Crook, ORWest Sep 2021target 2025
Other project G0969, Linn County
Other
160 MWIn study Linn, ORWest Oct 2023target 2028
Other project G0970, Polk County
Other
160 MWIn study Polk, ORWest Oct 2023target 2028
Other project G0971, Lane County
Other
160 MWIn study Lane, ORWest Oct 2023target 2028
Other project G0886, Linn County
Other
160 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0794, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Other project G0793, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Other project G0877, Lane County
Other
80.0 MWIn study Lane, ORWest Jun 2023target 2029
Other project G0883, Lane County
Other
80.0 MWIn study Lane, ORWest Jun 2023target 2029
Other project G0885, Linn County
Other
80.0 MWIn study Linn, ORWest Jun 2023target 2029
Other project 11-042, Jefferson County
Other
37.0 MWPaused / redesign Jefferson, ORWest Jun 2011target 2013
Other project G0505, Lincoln County
Other
20.0 MWIn study Lincoln, ORWest Jan 2015target 2017
Other project 07-018, Jefferson County
Other
18.5 MWPaused / redesign Jefferson, ORWest Aug 2007target 2010
Other project 09-034, Jefferson County
Other
18.5 MWPaused / redesign Jefferson, ORWest Apr 2009target 2013
Other project hist_q12, Grant County
Other
10.0 MWPaused / redesign Grant, ORWest

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)