United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown92,623 MW
Active in queue4,676 MW21 requests
Agreement signed1,535 MW5 requests
Withdrawn92,623 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-087, Rogers County
Gas
510 MWWithdrawn / abandoned Rogers, OKSPP Oct 2024target 2029
Gas project GEN-2024-012, Oklahoma County
Gas
496 MWWithdrawn / abandoned Oklahoma, OKSPP Aug 2024target 2029
Solar project GEN-2024-GR2, Chouteau County
Solar
442 MWWithdrawn / abandoned Chouteau, OKSPP Feb 2024target 2026
Solar project GEN-2024-075, Woodward County
Solar
300 MWWithdrawn / abandoned Woodward, OKSPP Oct 2024target 2029
Onshore wind project GEN-2024-060, Nowata County
Onshore wind
250 MWWithdrawn / abandoned Nowata, OKSPP Oct 2024target 2029
Solar project GEN-2024-031, Marshall County
Solar
220 MWWithdrawn / abandoned Marshall, OKSPP Oct 2024target 2028
Onshore wind project GEN-2024-070, Okfuskee County
Onshore wind
185 MWWithdrawn / abandoned Okfuskee, OKSPP Oct 2024target 2028
Solar project GEN-2024-086, Jackson County
Solar
120 MWWithdrawn / abandoned Jackson, OKSPP Oct 2024target 2029
Solar + storage project GEN-2024-024, Woodward County
Solar + storage
100 MWWithdrawn / abandoned Woodward, OKSPP Oct 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)