πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown132,294 MW
Active in queue2,241 MW14 requests
Agreement signed2,241 MW14 requests
Withdrawn132,294 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2018-005, Haskell County
Solar
500 MWWithdrawn / abandoned Haskell, OKSPP Apr 2018target 2021
Onshore wind project GI-65, Mayes County
Onshore wind
500 MWWithdrawn / abandoned Mayes, OKSoutheast Mar 2018target 2020
Solar project GEN-2018-127, Logan County
Solar
200 MWWithdrawn / abandoned Logan, OKSPP Nov 2018target 2021
Onshore wind project GI-63, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSoutheast Jan 2018target 2020
Solar project GEN-2018-076, Logan County
Solar
200 MWWithdrawn / abandoned Logan, OKSPP Oct 2018target 2021
Solar project GEN-2018-080, Craig County
Solar
200 MWWithdrawn / abandoned Craig, OKSPP Nov 2018target 2023
Solar project GEN-2018-117, Roger Mills County
Solar
150 MWWithdrawn / abandoned Roger Mills, OKSPP Nov 2018target 2026
Solar project GI-69, Kingfisher County
Solar
105 MWWithdrawn / abandoned Kingfisher, OKSoutheast May 2018target 2020
Solar project GEN-2018-021, Washita County
Solar
74.1 MWWithdrawn / abandoned Washita, OKSPP May 20182024
Battery storage project GEN-2018-109, Caddo County
Battery storage
50.0 MWWithdrawn / abandoned Caddo, OKSPP Nov 2018target 2020
Gas project GEN-2018-034, Mayes County
Gas
40.0 MWWithdrawn / abandoned Mayes, OKSPP May 2018target 2018
Battery storage project GEN-2018-098, Caddo County
Battery storage
40.0 MWWithdrawn / abandoned Caddo, OKSPP Nov 2018target 2021
Battery storage project GEN-2018-051, Muskogee County
Battery storage
35.0 MWWithdrawn / abandoned Muskogee, OKSPP May 20182025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)