United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown81,178 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn81,178 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2013-038, Canadian County
Onshore wind
300 MWWithdrawn / abandoned Canadian, OKSPP Dec 2013target 2016
Onshore wind project GEN-2013-036, Delaware County
Onshore wind
250 MWWithdrawn / abandoned Delaware, OKSPP Dec 2013target 2016
Onshore wind project GEN-2013-037, Grady County
Onshore wind
250 MWWithdrawn / abandoned Grady, OKSPP Dec 2013target 2016
Onshore wind project GEN-2013-035, Woodward County
Onshore wind
106 MWWithdrawn / abandoned Woodward, OKSPP Dec 2013target 2016
Onshore wind project GEN-2013-009, Craig County
Onshore wind
100 MWWithdrawn / abandoned Craig, OKSPP Mar 2013target 2015
Onshore wind project GEN-2013-034, Ellis County
Onshore wind
73.6 MWWithdrawn / abandoned Ellis, OKSPP Sep 2013target 2014
Onshore wind project GEN-2013-025, Canadian County
Onshore wind
50.0 MWWithdrawn / abandoned Canadian, OKSPP Sep 2013target 2015
Gas project GEN-2013-003, Woodward County
Gas
48.0 MWWithdrawn / abandoned Woodward, OKSPP Mar 2013target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)