United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,688 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn101,688 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2010-028, Blaine County
Onshore wind
335 MWWithdrawn / abandoned Blaine, OKSPP May 2010target 2013
Gas project GEN-2010-043, Woodward County
Gas
320 MWWithdrawn / abandoned Woodward, OKSPP Sep 2010target 2017
Onshore wind project GEN-2010-002, Canadian County
Onshore wind
300 MWWithdrawn / abandoned Canadian, OKSPP Mar 2010target 2012
Onshore wind project GEN-2010-004, Murray County
Onshore wind
202 MWWithdrawn / abandoned Murray, OKSPP Mar 2010target 2011
Onshore wind project GEN-2010-030, Major County
Onshore wind
150 MWWithdrawn / abandoned Major, OKSPP May 2010target 2014
Onshore wind project GEN-2010-018, Beckham County
Onshore wind
101 MWWithdrawn / abandoned Beckham, OKSPP Mar 2010target 2011
Onshore wind project GEN-2010-023, Woodward County
Onshore wind
99.0 MWWithdrawn / abandoned Woodward, OKSPP Mar 2010target 2012
Onshore wind project GEN-2010-012, Roger Mills County
Onshore wind
65.0 MWWithdrawn / abandoned Roger Mills, OKSPP Mar 2010target 2012
Onshore wind project GEN-2010-008, Woodward County
Onshore wind
64.4 MWWithdrawn / abandoned Woodward, OKSPP Mar 2010target 2011
Onshore wind project GEN-2010-019, Carter County
Onshore wind
52.2 MWWithdrawn / abandoned Carter, OKSPP Mar 2010target 2011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)