Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown292.8 MW
Active in queue3,146 MW26 requests
Agreement signed2,650 MW22 requests
Withdrawn576,262 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Rolling Hills Generating
Gas
89.6 MWOperating Vinton, OHPJM Mar 20202023
Northwest Ohio Wind
Solar + storage
3.2 MWOperating Paulding, OHPJM Mar 20202021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)