United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in North Dakota (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5954 MW
Active in queue954 MW5 requests
Agreement signed851 MW4 requests
Withdrawn5938 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Onshore wind project MPC03900, Eddy County
Onshore wind
151 MWAgreement signed Eddy, NDMISO Apr 2019target 2027
Solar project GEN-2019-037, Mercer County
Solar
150 MWAgreement signed Mercer, NDSPP May 2019target 2023
Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2
Gas
103 MWIn study Morton, NDMISO Jun 20192024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)