Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4805 MW
Active in queue805 MW4 requests
Agreement signed555 MW3 requests
Withdrawn81,307 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Solar project MPC03600, Richland County
Solar
170 MWAgreement signed Richland, NDMISO May 2018target 2027
Solar project MPC03700, Richland County
Solar
130 MWAgreement signed Richland, NDMISO May 2018target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)